For information on our pharmaceutical capability, please contact Stephen Taylor.
Eastman Peboc
Primary pharmaceutical manufacturing expansion
Anglesey, UK
![[Eastman Peboc primary expansion]](graphics/east_exp.jpg)
The new plant was constructed on an existing operating chemicals site, and included reactors, centrifuge, dryer, hydrogenation, filteration and other ancilliary equipment.
CEL responsibilities
- Conceptual, front end and detailed design
- Project management
- Procurement
- Construction
- Validation
Key features
- Decommissioning of existing plant
- Strip-out of all equipment and extension to building
- Fitout/installation of new cGMP plant
- ‘Love the plant’ KPI for operators
- Control, operability and ergonomics emphasis
Return to our pharmaceutical project experience.
Return to our pharmaceutical capability.
![[CEL logo]](../graphics/logo.gif)