Courtaulds Fibres
12MW CHP plant
Grimsby, UK
![[Courtaulds Fibres CHP, Grimsby]](graphics/courtchp.jpg)
This project comprised a new CHP plant together with steam distribution to the production plant and a major revision of the HV infrastructure.
CEL responsibilities
- Design and engineering
- Project management
- Construction
- Commissioning
Key features
- Open book reimbursable contract
- Long-term parallel operation with grid
- Water injection for NOx suppression
Return to our energy and environment project experience.